Navigating the NSW Planning System: Exempt vs Complying vs DA for Glamping Sites

Exempt development, complying development, or a full DA โ€” which approval pathway does your NSW glamping site actually need? Here's how to figure out which lane you're in before you build anything.

By Jesse Anyan

Founder of Glamporise

TL;DR

NSW glamping projects fall into one of three approval pathways โ€” exempt development (no approval needed if you meet every standard), complying development (fast-tracked certificate through council or a certifier), or a development application (full council assessment for larger or more complex projects). Which lane you’re in depends on your zoning, property size, guest numbers, and what you want to build. Getting this wrong is expensive. Getting it right early is not.

Paperwork Is Cheaper Than Pulling Down Tents

A lot of new glamping operators start quietly, hoping council won’t notice. Some get away with it for a while. Most eventually get a letter they weren’t expecting.

Understanding which approval pathway applies to your project isn’t about being cautious โ€” it’s about building something that lasts. A stop-work order after you’ve installed platforms, run power, and set up three domes is a far more expensive lesson than an hour spent getting the planning right upfront.

NSW has three distinct pathways for glamping approvals. Once you understand how they work and which one fits your situation, the system becomes genuinely navigable.

Follow Us:

More Posts

Subscribe to our Newsletter:

The Three Pathways at a Glance

The State Environmental Planning Policy (Codes SEPP) sets out three categories of development based on size, impact, and compliance with prescribed standards.

Exempt Development โ€” No planning or building approval required. If your project meets every prescribed standard, you can proceed without lodging anything with council. Miss one requirement, and you drop out of exempt entirely.

Complying Development โ€” A combined planning and construction approval, assessed by your local council or an accredited private certifier. Faster than a DA, but still requires plans, fees, and assessment against the Codes SEPP.

Development Application (DA) โ€” The standard council assessment process for projects that don’t fit exempt or complying categories. Involves detailed plans, reports, community notification, and a council determination. Takes longer, costs more, but opens the door to larger and more complex operations.

The right pathway for your project depends on your zoning, property size, what you want to build, your guest numbers, and whether you’re on a qualifying farm.

Exempt Development โ€” The Fast Lane for Small Operators

Exempt development is the best-case outcome for eligible glamping operators. No fees, no lodgement, no waiting. If your project meets every standard, you can move.

Who It’s For

Exempt development under the agritourism framework is available to working farms of at least 15 hectares in RU1, RU2, or RU4 zones. If your property doesn’t meet those criteria, this pathway isn’t available to you โ€” but other options exist (more on that below).

For qualifying farms, the kinds of projects that work well under exempt development include:

  • A single dome or a small number of luxury tents with composting toilets
  • A few self-contained glamping structures with proper setbacks and guest caps managed carefully
  • Low-impact, minimal-infrastructure setups where guests are largely self-sufficient

The Standards You Must Meet โ€” Every Single One

  • Maximum 20 guests at any one time
  • Maximum 21 consecutive days per individual stay
  • Maximum 6 caravans or campervans on site simultaneously
  • Self-containment โ€” if no communal toilets are provided, guests must bring their own
  • Bushfire evacuation signage on bushfire-prone land
  • Setbacks from property boundaries, water bodies, and roads per the Codes SEPP
  • Building Code compliance โ€” decks, platforms, and footings all still need to meet structural standards
  • No prohibited environmental overlays โ€” floodways and drinking water catchments may exclude you

The critical thing to understand about exempt development: it’s all or nothing. You meet every standard, or you don’t qualify. There’s no partial credit.

What Exempt Development Is Good For

Speed. You can launch a small glamping operation without waiting months for council assessment.

Low cost. No planning or certification fees, beyond any building code compliance costs for structures.

Market testing. Starting under exempt development is a practical way to test demand before committing to a larger, more expensive operation.

Where It Falls Short

The 20-guest cap limits revenue potential as a standalone business. And because you’re self-certifying your compliance, a single mistake โ€” an extra guest, a deck that’s slightly too large, a composting toilet installed without the right approval โ€” can drop you out of exempt status and into compliance action.

๐Ÿ’ก Worth knowing: Building a yoga deck or additional communal structure that exceeds the exempt development standards for structures will take your whole project out of the exempt category โ€” even if your guest numbers and tent setup were otherwise fine.

ย 


ย 

Complying Development โ€” The Middle Road

Complying development is the pathway for projects that are more involved than exempt development but still operate within defined, assessable standards. It combines planning and building approval into a single certificate โ€” issued by your council or a private certifier.

When Complying Development Makes Sense

Consider a Complying Development Certificate (CDC) if:

  • You want more guests or more tents than the exempt caps allow
  • You’re planning a communal amenities block, shared kitchen, or other permanent structure
  • You’re in a zone where farm stay accommodation is permissible with consent but not as exempt development
  • You need minor variations from setback or infrastructure standards

The Process

Step 1 โ€” Prepare your documents. Site plans, floor plans, elevations, engineering details, and wastewater design. Depending on your project, you may also need a BASIX certificate and environmental reports.

Step 2 โ€” Engage a certifier. Your local council or a private certifier assesses your application against the Codes SEPP.

Step 3 โ€” Submit and pay. Lodge your application with the required plans and fees.

Step 4 โ€” Assessment. If your proposal meets the standards, you receive a CDC. If it doesn’t, you’ll need to modify your design or move to a DA.

Turnaround time is typically within 20 business days when documentation is complete โ€” significantly faster than a DA.

What Complying Development Is Good For

Modest expansion. Going from two tents and 12 guests to seven tents and 24 guests with a shared bathroom โ€” this is the complying development sweet spot.

Predictability. Unlike a DA, there’s no council discretion in the assessment. If you meet the standards, you get the certificate. Full stop.

Manageable cost. More expensive than exempt development, but a fraction of what a DA costs in professional fees and time.

Where It Falls Short

If your project exceeds the complying development standards โ€” guest numbers, structure size, environmental sensitivity โ€” you’re into DA territory. And not all zones or locations permit complying development at all.

Development Application โ€” The Full Council Process

A DA is required when your project doesn’t fit within exempt or complying development standards. It involves submitting detailed plans and reports to council, a public assessment period, and a formal council determination.

When a DA Is Required

  • Your land doesn’t meet the agritourism eligibility criteria (under 15 ha, wrong zone, non-farming property)
  • You want more than 20 guests or more than 6 caravans/campervans
  • You’re building permanent structures โ€” cabins, restaurants, large communal spaces
  • You need significant earthworks, vegetation clearing, or major infrastructure
  • Your site is in a sensitive location โ€” floodplain, drinking water catchment, heritage area, coastal zone

The DA Process Step by Step

Pre-lodgement meeting. Book a meeting with council before you prepare anything. They’ll flag key issues, required reports, and likely conditions. This step saves significant time and money.

Engage your team. Depending on complexity, you may need a town planner, architect, bushfire consultant, civil engineer, traffic engineer, and ecologist. A larger project genuinely needs this team.

Prepare your DA package. Typically includes: site analysis, architectural drawings, statement of environmental effects, waste management plan, bushfire assessment, and potentially an ecological impact assessment and acoustic report.

Community notification. Most DAs are exhibited publicly for 14โ€“28 days. Neighbours can make submissions. Council takes these seriously.

Assessment and determination. Council planners review your proposal against the LEP, Development Control Plan (DCP), and relevant policies. A recommendation goes to a delegated officer or local planning panel.

Conditions of consent. If approved, your consent comes with conditions โ€” operating hours, landscaping, traffic management, water and waste requirements. These form the ongoing rules of your operation.

Construction certificate. Before building anything, you also need a Construction Certificate verifying your plans meet the Building Code of Australia.

What the DA Route Enables

The DA pathway is the route to a genuinely large or complex glamping operation โ€” 15 domes, a yoga pavilion, communal dining, a plunge pool. Things that simply aren’t achievable through exempt or complying development.

It’s also the only pathway for non-farm properties, coastal zones, and locations with environmental sensitivities.

The Honest Downsides

Time. A DA can take six to twelve months or longer. Cost. Professional fees alone for a complex project can run into tens of thousands of dollars. And approval is never guaranteed โ€” council can refuse, request redesigns, or impose conditions that change your business model significantly.

Which Pathway Is Yours? A Quick Decision Guide

ScenarioExempt?Complying?DA?
Working farm, 15+ ha, RU zone, 3 tents, 12 guests, composting toilets, no amenities blockโœ… YesNot neededNot needed
Working farm, 15+ ha, RU zone, 7 tents, 24 guests, communal bathroomโŒ Noโœ… YesNot needed if within standards
Hobby farm, 10 ha, R5 zone, 4 domesโŒ NoโŒ Noโœ… Yes
Working farm, 50 ha, RU2, 10 safari tents, 35 guests, communal kitchenโŒ NoโŒ Noโœ… Yes
Non-farm rural property, coastal zone, boutique eco-retreatโŒ NoโŒ Noโœ… Yes

Use this as your starting point. The Codes SEPP has the full detail, and specific property circumstances always matter.

What If You're Not on a Qualifying Farm?

The agritourism pathway requires a working farm of 15+ hectares in the right zone. If that’s not you, the exempt and complying pathways under agritourism don’t apply โ€” but glamping is still possible.

Tourist and visitor accommodation โ€” most LEPs have a separate classification for this land use. You’ll need a DA, but it’s a viable pathway for rural residential and non-farm properties.

Camping grounds โ€” some councils permit camping grounds on rural land that doesn’t qualify as agritourism. Again, a DA is required.

Moveable dwellings โ€” tiny houses, modular pods, and relocatable cabins are classified differently from tents. They can sometimes be approved as secondary dwellings or under caravan park regulations. They offer a more permanent product and may suit lifestyle properties better than a tent-based operation.

The DA route is longer and more expensive than agritourism pathways. But it’s the route many successful glamping businesses in NSW have taken โ€” particularly those operating in non-farming settings.

Practical Tips for Whichever Path You Take

Talk to council early. A pre-lodgement conversation costs nothing and can save months of rework. Even for exempt projects, a quick call to confirm your interpretation is worthwhile.

Document your compliance. Keep records of your property eligibility โ€” farm status, land size, zoning โ€” and your ongoing compliance โ€” guest numbers, stay duration, building details. If council ever questions you, having that documentation ready is the difference between a quick conversation and an investigation.

Start small, expand deliberately. Most successful glamping operators start with one or two units under exempt or complying development, prove the concept, then scale up with a DA. This approach manages risk and lets you build a track record before committing to a major project.

Keep neighbours in the loop. A single complaint to council can trigger a compliance check. Most neighbour concerns are about noise, traffic, and visual impact. Addressing these proactively โ€” before you open โ€” is far easier than managing them after the fact.

Your Next Step

Understanding which approval pathway applies is the decision that shapes everything else โ€” your design, your timeline, your budget, and your opening date. It’s also the question the NSW Glamping Planning Pathway is built to help you answer, whether you need a $27 self-guided property check or full done-for-you planning support.

(See all four stages and find the one that fits your situation.)

Keep Reading

This is the first in a series of guides walking NSW landowners through the glamping planning process from start to finish. Next up:

Bushfire Basics for NSW Glamping Sites: BAL Ratings, Fire Safety and What Council Actually Expects

30 JUNE 2026 Bushfire Basics for NSW Glamping Sites: BAL Ratings, Fire Safety and What Council Actually Expects Bushfire planning isn’t optional for NSW glamping operators โ€” it shapes your site layout, your structures, and your approval pathway. Here’s what BAL ratings mean and what every glamping site needs to have in place. By Jesse Anyan Founder of Glamporise TL;DR Most rural NSW properties sit on bushfire-prone land. For glamping operators, that means a Bush Fire Attack Level (BAL) assessment is required as part of your planning and building approvals โ€” and your BAL rating determines everything from your setbacks

Read More โ†’

Water, Waste and Toilets: The Unglamorous Systems That Make or Break Your NSW Glamping Site

30 JUNE 2026 Water, Waste and Toilets: The Unglamorous Systems That Make or Break Your NSW Glamping Site No one books a glamping trip for the sewage system. But water, waste, and toilets are the systems that determine whether your NSW glamping site stays open โ€” or gets shut down. Here’s what you need to know. By Jesse Anyan Founder of Glamporise TL;DR Every NSW glamping site needs three things sorted before guests arrive: safe drinking water, a compliant waste system, and enough water on hand for firefighting. Whether you go traditional (septic, mains connection) or eco-friendly (composting toilets, greywater

Read More โ†’

The Hidden Permits Most NSW Glamping Operators Miss: Section 68 Approvals Explained

30 JUNE 2026 The Hidden Permits Most NSW Glamping Operators Miss: Section 68 Approvals Explained You’ve got your DA sorted โ€” but did you know a separate council permit may be required before you install a composting toilet, a moveable dwelling, or a water tank? Here’s what Section 68 covers and why glamping operators keep getting caught out by it. By Jesse Anyan Founder of Glamporise TL;DR Section 68 of the Local Government Act 1993 requires a separate council approval for specific activities โ€” including installing moveable dwellings, setting up water and waste systems, and operating on-site sewage management. This

Read More โ†’